On January 10, signed a cooperation framework agreement with Jianglu, Hunan

In March, sensor packaging line equipment entered the site one after another for installation

In April, signed a research and development contract for 6 models of products with Jianglu, Hunan

In June, the product was recognized by customers in Jianglu, Hunan, and began to purchase in small quantities

In October, the sensor package line was pulled through

In December, the sensor packaging line was mass-produced in small batches, 1500 pcs/day